![background image](http://html.mh-extra.com/html/nec/univerge-neax-2000-ips/univerge-neax-2000-ips_installation-manual_251421088.webp)
CHAPTER 2 INSTALLATION
– 72 –
NWA-008841-001 Rev.5.0
90ch2001.fm
PROCEDURE
This flowchart explains the procedures for installing the PBX system. You should follow the procedure
shown below.
Procedure Flowchart
Continued on next page
START
UNPACKING
INSTALLATION
OF
MAIN EQUIPMENT
BATTERY
CONNECTION
TERMINATION OF
CABLES ON MDF
SUPPLY VOLTAGE CHECK
AND
HEAT RUN TEST
CABLE RUNNING
TO MDF
INSTALLATION
OF
PERIPHERAL EQUIPMENT
A
POWER CABLE
CONNECTION
SWITCH SETTINGS
OF
CIRCUIT CARDS
REFER TO
“CHAPTER 3”
Page 289
Page 75
Page 82
Page 111
Page 121
Page 129
Page 137
Page 144
Page 173
WIRING AC CABLE
TO
TERMINALS
Page 76
PROCEDURE