Expansion Cabinet CAN Bus Cabling
Chapter 5: Interconnection and Internal Cabling
Expansion Cabinet CAN Bus Cabling
lists the CAN Bus Cabling for MTS 4 with Expansion Cabinet.
Table 5-30
CAN Bus Cabling for MTS 4 with Expansion Cabinet
Index
Cable Part
Number
From Unit
To Unit
Notes
A
3066544B09
Duplexer or PostFilter /
CAN2
ATCC 2 / CAN1
Prime Cabinet
H
3066544B09
ATCC 2 / CAN2
ATCC 1 / CAN1
Prime Cabinet
F
3066544B03
ATCC 1 / CAN2
PSU 2 / CAN1
Prime Cabinet
F
3066544B08
PSU 2 / CAN 2 (Prime
Cab)
PSU 3 / CAN1 (Exp
Cab)
In all con
fi
gurations
PSU 3 / CAN2 (Exp Cab)
Joint 1
If only one PSU and no
ATCC in Exp Cab
PSU 3 / CAN2 (Exp Cab)
PSU 4 / CAN1
If two PSUs in Exp Cab
F
3066544B06
PSU 3 / CAN2 (Exp Cab)
ATCC 3 / CAN1
If one PSU and ATCC in
Exp Cab
PSU 4 / CAN2 (Exp Cab)
Joint 1
If no ATCC in Exp Cab
F
3066544B06
PSU 4 / CAN2 (Exp Cab)
ATCC 3 / CAN1
If ATCC in Exp Cab
F
ATCC 3 / CAN2
Joint 1
If one ATCC in Exp Cab
H
3066544B09
ATCC 3 / CAN2
ATCC 4 / CAN1
If two ATCC in Exp Cab
3066544B06
ATCC 4 / CAN2
Joint 1
If two ATCC in Exp Cab
Joint 1
CAN Bus
termination
Without redundant Site
Controller
F
3066544B03
Joint 1
SC 2/ CAN
With redundant Site
Controller / red cable
CAN Bus cables from Prime Cabinet to Expansion Cabinet are routed through
the conjunction hole on the side of the cabinets.
5-58
6802800U74-N September 2009
Summary of Contents for DIMETRA MTS 2
Page 4: ...This page intentionally left blank ...
Page 28: ...List of Procedures This page intentionally left blank xxii 6802800U74 N September 2009 ...
Page 30: ...List of Processes This page intentionally left blank xxiv 6802800U74 N September 2009 ...
Page 486: ...This page intentionally left blank A 10 6802800U74 N September 2009 ...
Page 492: ...This page intentionally left blank B 6 6802800U74 N September 2009 ...
Page 496: ...This page intentionally left blank C 4 6802800U74 N September 2009 ...