8.3 Processing
Time
Processing time is measured from when an input signal enters the input module until it is output
from the output module. That time is the sum of (1) to (4) shown below.
Input module
CPU module
Output
module
External
input signal
External
output signal
Remote I/O line
Remote I/O line
Input delay
Ladder
processing
time
(10 to 999 ms)
Output delay
Transfer
time
(5 to 21 ms)
Transfer
time
(5 to 21 ms)
(
1
)
(
2
)
(
3
)
(
2
)
(
4
)
(1) Input
delay
An input delay is taken by the input module to respond. The response time varies with the type
of the input module. For details, refer to the “S10mini HARDWARE MANUAL I/O
MODULE (manual number SME-1-114).”
(2) Remote I/O transfer time
The remote I/O transfer time is taken for data transfer on the remote I/O line. That time varies
with the specified number of I/O points.
512 points: About 5 ms
1024 points: About 10 ms
1536 points: About 16 ms
2048 points: About 21 ms
(3) Ladder processing time
The ladder processing time is taken by the ladder diagram program for processing. That time is
equal to the sequence cycle time (10 to 999 ms).
(4) Output
delay
An output delay is taken by the output module to respond. The response time varies with the
type of the output module. For details, refer to the “S10mini HARDWARE MANUAL I/O
MODULE (manual number SME-1-114).”
Calculate the processing time using the following formula:
Processing time = (input delay) + (RI/O transfer time) + (ladder processing time) +
(RI/O transfer time) + (output delay)
Summary of Contents for S10mini D
Page 1: ......
Page 14: ...THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 19: ...1 BEFORE USE ...
Page 28: ...THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 29: ...2 OVERVIEW ...
Page 34: ...THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 35: ...3 NAMES AND FUNCTIONS OF PARTS ...
Page 45: ...4 INSTALLATION ...
Page 54: ...THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 55: ...5 WIRING ...
Page 68: ...THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 69: ...6 SETTING ...
Page 84: ...THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 85: ...7 OPERATION PROCEDURES ...
Page 91: ...8 EXPLANATION OF OPERATION ...
Page 111: ...9 MAINTENANCE ...
Page 128: ...THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 129: ...10 SPECIFICATIONS ...