3.5.2 Repair procedures
To remove the fan inverter PCB
1
As there is no separate spare part for the inverter PCB and fan inverter PCB,
these need to be replaced as one complete assembly. See
89].
To install the fan inverter PCB
1
As there is no separate spare part for the inverter PCB and fan inverter PCB,
these need to be replaced as one complete assembly. See
89].
2
Clean the heat sink surface and apply a thin layer of heat sink compound to
the heat sink surface.
3
Install the fan inverter PCB on its correct location.
4
Latch the PCB supports using a small pair of pliers to fix the PCB.
5
Install and tighten the 2 screws to fix the fan inverter PCB to the heat sink
plate.
a
b
b
a
d
c
a
a
a
Connector
b
Screw
c
Connector X1A
d
Connector X4A
6
Connect all connectors to the fan inverter PCB.
7
Reinstall connector X4A which you recuperated from the removed PCB.
Is the problem solved?
Action
Yes
No further actions required.
No
74] of the fan inverter
PCB and continue with the next
procedure.
3.6 High pressure switch
3.6.1 Checking procedures
To perform an electrical check of the high pressure switch
Prerequisite:
Stop the unit operation via the user interface.
Prerequisite:
Turn OFF the respective circuit breaker.
Prerequisite:
Remove the required plate work, see
111].
Summary of Contents for Sky Air Advance RZA200D7Y1B
Page 1: ...Service manual Sky Air Advance series RZA200D7Y1B RZA250D7Y1B ...
Page 190: ......
Page 191: ......
Page 192: ...ESIE19 13A 2020 05 Copyright 2020 Daikin Verantwortung für Energie und Umwelt ...