Chapter 3
:
Installation
32
SE505 Hardware Manual
Unpacking the SE505 System
These instructions describe how to unpack the SE505 system from its shipping crate. It is
recommended to save the crate and all of the packing materials.
Performing this procedure requires a drill with a 13 mm socket attachment, a forklift, and a
pallet jack. Capacity of forklift: (826 kg, 185 cm).
➢
To unpack the SE505 system
1. Using the drill and a 13 mm socket attachment, remove all the hex head bolts marked in blue
from the panel where there is a label indicating “To uncrate remove blue bolts” as shown.
2. Remove the panel with the label indication from the platform or skid/pallet.
3. Slide out the remaining crate pocket off the platform.
4. Using the drill and socket attachment, remove the hex head bolts from the lockdown plate
located at each of the leveling feet.
5. Remove the packing material, moisture barriers, desiccants and accessories around the unit.
6. From the rear of the machine, ensure the forklift’s forks are supporting both crossbeams
under the system before lifting.
7. Lift the machine off the crate base.
Warning:
Only CyberOptics’ service personnels shall perform the installation procedures in
this Chapter.
13 mm socket attachment
i
Note:
The machine should be at room temperature before removing the moisture
barriers.
i
Note:
The forks must properly support both crossbeams from the rear of the machine. If not,
the machine may tip over while being moved.
Summary of Contents for SE505
Page 1: ...SE505 Hardware Manual ...
Page 6: ...Contents vi SE505 Hardware Manual ...
Page 10: ...x SE505 Hardware Manual ...
Page 72: ...Chapter 3 Installation 62 SE505 Hardware Manual ...
Page 168: ...Chapter 4 Replacing Components and Preventive Maintenance 158 SE505 Hardware Manual ...
Page 180: ...Index 170 SE505 Hardware Manual ...