8 Commissioning instructions
8.1 What this chapter contains
This chapter presents the steps to follow to commission the inverter. The
commissioning of your ESI should be conducted in strict accordance with this
procedure.
Before applying the commissioning procedure, make sure that you are familiar with:
- The inverter hardware (discussed in
Chapter 4
- The mechanical installation requirements (discussed in
- The electrical installation requirements (discussed in
- The ESI programming interface ESI-Manager (discussed in
-
If the Modbus option has been installed, please refer to the document
“2GCS212013A0050-RS-485 Installation and Start-up guide” for more information on
this item.
The commissioning procedure consists of 9 steps that should be strictly followed.
Table 53: Steps to follow to commission the inverter
Steps Actions
Step 1 Visual and installation check
Step 2 Setting the address of each unit in a multi-unit inverter and terminate the CAN bus
Step 3 Voltage rating and phase rotation check
Step 4 Basic commissioning parameters setup
Step 5 Automatic and manual CT detection procedure if CT are connected
Step 6 Before starting the inverter
Step 7 Start the inverter
Step 8 Generate inverter load
Step 9 Set up the user requirements
Section 8.11
presents the commissioning report to be filled in when commissioning
the inverter.