Page 18
T47541109 Rev. J
FlexJet Head Assembly
TECHNICAL
PUBLICATIONS
This Document Supports Assembly 47541109 Rev. F
4.
Power up the machine.
5.
After the machine initializes, select
System Setup > Machine >
Setup > Zero Axes
. The machine zeros. If the machine does not
complete zeroing, check
Machine Status > Display Status >
Current Messages
for error messages.
6.
Push an E-stop button (palm down) and install the feeders removed
earlier. Ensure that they match the feeder configuration in UPS.
7.
Palm up, open a product in UPS and dry cycle the head for verification.
8.
Perform calibrations as recommended in the maintenance procedure.
9.
Record on the appropriate copied sheet from the Maintenance Log
document that the procedure was performed and include the date.
Installing the FlexJet Head
Install a FlexJet Head using the following procedure. If a FlexJet Head has
not previously been installed on the machine, contact a Universal Technical
Specialist to ensure that the machine has the hardware installed to ensure
proper functioning of the head.
Prerequisites
The platform machine must have 4.x Universal Platform Software (UPS).
Ensure that the following items are available before beginning the procedure.
• For a new head installation, obtain a Calibration Kit for FlexJet and
a Calibration Placement Enhancement (CPE) Kit for FlexJet
For a head installation in the previous position, obtain a Calibration
Placement Enhancement (CPE) Kit for FlexJet
• PC Jumper Config., SMT document; Calibration, CPE and
Measurement manual
• Loctite 222 and a torque wrench
• An ESD grounded wrist strap