AFP-400 Installation
PN
50253
:
A2 03/12/96
2-3
Installation Tasks
o
Check AC power
Apply AC power to the AFP-400, but do not connect
batteries at this time. Silence the audible trouble sounder by pushing the
Acknowledge switch on the CPU-400. The AFP-400 should reflect the
following status:
Component
Status
The CPU-400
The green AC Power indicator on; System Trouble
indicator on because of no battery power.
Each module
The yellow Trouble indicator may come on for
approximately 10 seconds after applying AC power.
(This only applies to an unconfigured system.)
Each AVPS-24
The yellow Trouble indicator comes on because batteries
are not connected.
o
Program the AFP-400
Configure and program the system, refer to the
AFP-400 Programming Manual, Document 50259.
Connect Batteries
Once the system is programmed and is functional,
connect the batteries. Make sure that all indicators, except AC POWER,
are extinguished.
o
Test the system
Fully field test the system by conducting the test
procedure in Section 3, Testing the System.
o
Install Dress Panels
Complete installation of the AFP-400 system by
installing all remaining dress panels.