6 Commissioning
Maschinenfabrik Reinhausen GmbH 2020
161
4349322/01 EN
VACUTAP
®
VV
®
3. Discharge the gas from under the on-load tap-changer cover. Ensure suf-
ficient fresh air (e.g. in transformer cells and work tents) when doing so.
4. Once the gas has been discharged and the insulating fluid is flowing out
of the air-vent valve, close the air-vent valve and close the stop-cock be-
tween the oil conservator and oil compartment.
5. Open air-vent valve again and drain off approximately 5–10 liters of insu-
lating fluid via the pipe connection S until the area under the on-load tap-
changer head cover is free of insulating fluid.
6. Loosen 24 screws M10 / wrench size 17 with locking elements on the on-
load tap-changer head cover.
7. Remove on-load tap-changer head cover.
8. Extract insulating fluid via pipe connection S.
9. Open stop-cock between oil conservator and oil compartment.
ð
Insulating fluid flows out of the oil conservator into the oil compartment.
10. Extract insulating fluid via pipe connection S.
11. Place on-load tap-changer head cover on the on-load tap-changer head.
12. Screw down on-load tap-changer head cover using 24 screws M10 /
wrench size 17 and locking elements (tightening torque 34 Nm).
6.2.3.2 Emptying oil compartment without oil suction pipe
WARNING
Danger of explosion!
Explosive gases under the on-load tap-changer head cover can deflagrate
or explode and result in severe injury or death.
► Ensure that there are no ignition sources such as open flames, hot sur-
faces or sparks (e.g. caused by the build-up of static charge) in the imme-
diate surroundings and that none occur.
► De-energize all auxiliary circuits (for example tap-change supervisory de-
vice, pressure relief device, pressure monitoring device) before removing
the on-load tap-changer head cover.
► Do not operate any electrical devices during the work (e.g. risk of sparks
from impact wrench).
1. De-energize all auxiliary circuits (for example the tap-change supervisory
control, pressure relief device, pressure-operated relays).
2. If the stop-cock (slide valve) between the oil conservator and oil compart-
ment is open, open the air-vent valve E1 on the on-load tap-changer
head.
3. Drain off the gas from under the on-load tap-changer cover. Ensure suffi-
cient fresh air (for example in transformer cells and work tents).
4. Once the gas has been drained off and the oil is flowing out of the air-vent
valve, close this valve and close the stop-cock between the oil conserva-
tor and oil compartment.
Содержание VACUTAP VV
Страница 1: ...On load tap changer VACUTAP VV Installation and commissioning instructions 4349322 01 EN ...
Страница 112: ...5 Mounting Maschinenfabrik Reinhausen GmbH 2020 112 4349322 01 EN VACUTAP VV Figure 109 Mounting protective tube ...
Страница 125: ...5 Mounting Maschinenfabrik Reinhausen GmbH 2020 125 4349322 01 EN VACUTAP VV Figure 125 Angle of deflection α ...
Страница 182: ...9 Drawings Maschinenfabrik Reinhausen GmbH 2020 182 4349322 01 EN VACUTAP VV 9 Drawings ...
Страница 188: ......
Страница 195: ......
Страница 197: ......