6 Commissioning
Maschinenfabrik Reinhausen GmbH 2020
159
4349322/01 EN
VACUTAP
®
VV
®
▪ Remove leads used for testing before the high voltage test as these func-
tion as antennas.
▪ Wherever possible, route the measurement leads and data leads sepa-
rately to the energy cables.
Contact the manufacturer if you have any questions about possible sources
of danger.
6.2 Transporting transformer to the operating site
NOTICE
Damage to motor-drive unit!
Damage to the motor-drive unit due to condensate in protective housing of
motor-drive unit.
► Always keep protective housing of the motor-drive unit tightly closed.
► In the event of downtime lasting more than 8 weeks prior to initial com-
missioning, connect and operate the anti-condensation heater in the mo-
tor-drive unit. If this is not possible, place a sufficient amount of desiccant
in the protective housing.
6.2.1 Transport with drive removed
1. Ensure that the drive and the on-load tap-changer are in the adjustment
position.
2. Remove the drive.
3. Do not actuate the drive while the on-load tap-changer is uncoupled and
do not turn the output shaft.
4. Do not actuate an on-load tap-changer which is uncoupled and do not turn
its drive shaft.
5. Transport the drive to the installation site in the MR delivery packaging.
6. Fit the drive [
Section 5.4.5, Page 99] and the drive shaft [
5.4.6, Page 99] to the transformer at the installation site.
Содержание VACUTAP VV
Страница 1: ...On load tap changer VACUTAP VV Installation and commissioning instructions 4349322 01 EN ...
Страница 112: ...5 Mounting Maschinenfabrik Reinhausen GmbH 2020 112 4349322 01 EN VACUTAP VV Figure 109 Mounting protective tube ...
Страница 125: ...5 Mounting Maschinenfabrik Reinhausen GmbH 2020 125 4349322 01 EN VACUTAP VV Figure 125 Angle of deflection α ...
Страница 182: ...9 Drawings Maschinenfabrik Reinhausen GmbH 2020 182 4349322 01 EN VACUTAP VV 9 Drawings ...
Страница 188: ......
Страница 195: ......
Страница 197: ......