5-38
Cisco ONS 15454 SDH Procedure Guide, R7.0
78-17194-01
Chapter 5 Turn Up a Network
NTP- D344 Open-Ended SNCP Acceptance Test
b.
Connect the test set receive (Rx) connector to the circuit transmit (Tx) connector.
Step 13
Verify that the test set shows a clean signal. If a clean signal does not appear, repeat Steps
through
to make sure the test set and cabling are configured correctly.
Step 14
Inject BIT errors from the test set. To verify that you have a complete end-to-end circuit, verify that the
errors appear at the test set.
Step 15
Complete the
“DLP-D254 TCC2/TCC2P Card Active/Standby Switch Test” task on page 19-59
Step 16
Complete the
“DLP-D255 Cross-Connect Card Side Switch Test” task on page 19-60
.
Step 17
From the View menu, choose
Go to Network View
.
Step 18
Click one of the two spans leaving the circuit source node.
Step 19
Complete the
“DLP-D94 SNCP Protection Switching Test” task on page 17-91
to test the SNCP
protection switching function on this span.
Step 20
In network view, click the other circuit source span and repeat
Step 21
Set up and complete a BER test. Use the existing configuration and follow your site requirements for the
length of time. Record the test results and configuration.
Step 22
Complete the
“DLP-D27 Delete Circuits” task on page 17-21
Step 23
Remove any loopbacks, switches, or test sets from the nodes after all testing is complete.
Step 24
In network view, click the
Alarms
tab.
a.
Verify that the alarm filter is not on. See the
“DLP-D227 Disable Alarm Filtering” task on
as necessary.
b.
Verify that no unexplained alarms appear on the network. If unexplained alarms appear, resolve
them before continuing. Refer to the
Cisco ONS 15454 SDH Troubleshooting Guide
if necessary
.
c.
Complete the
“DLP-D147 Export CTC Data” task on page 18-38
to export the alarm information.
Step 25
In network view, click the
Conditions
tab.
a.
Verify that no unexplained conditions appear on the network. If unexplained conditions appear,
resolve them before continuing. Refer to the
Cisco ONS 15454 SDH Troubleshooting Guide
if
necessary.
b.
Complete the
“DLP-D147 Export CTC Data” task on page 18-38
to export the conditions
information.
Step 26
Repeat Steps
through
for each node that will be a source or destination for circuits traversing the
third-party network.
Step 27
If a node fails any test, repeat the test while verifying correct setup and configuration. If the test fails
again, refer to the next level of support.
After all tests are successfully completed and no alarms exist in the network, the network is ready for
service application. Continue with
Chapter 6, “Create Circuits and Low-Order Tunnels.”
Stop. You have completed this procedure.
Содержание ONS 15454 SDH
Страница 26: ...Tables vi Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 ...
Страница 62: ...xxii Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Страница 64: ...xxiv Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Страница 66: ...xxvi Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Страница 414: ...16 4 Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 Chapter 16 Power Down the Node NTP D114 Power Down the Node ...
Страница 832: ...A 14 Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 860: ...Index IN 28 Cisco ONS 15454 SDH Procedure Guide R6 0 78 17194 01 ...