Section 14. Troubleshooting Guide
and subsequently the radio will not detect the signal, the signal power is
between –95 and –115 dBm which is below the power limit for good data
transmission.
Similarly, if a 10 dBm attenuation pad is inserted in the link and the radio
subsequently will not detect the signal, the actual signal power is between –105
and –115 dBm. In this case, the signal power is far below the power limit.
Attenuation Pads
(10 - 20 dB)
Radio
Programmable
Scanner
To test the power being received by a radio over an RF link, disconnect the
radio from the antenna and insert the programmable scanner as shown in the
figure above. Program the scanner to the radio frequency and adjust the
squelch control until ambient RF noise is just cut out. This level will normally
be around –110 to –115 dBm. The scanner is now ready to conduct the test.
If you are using a data radio that does not have a transmit button
built in, you can easily build a push to transmit button from the
documentation of the radio/RF modem interface connector.
There will be one pin that when pulled high or pulled low will
initiate radio communication. See the radio documentation to
identify this pin. Connect a momentary push-button to either
raise or ground that pin.
Always make sure that the antenna is
connected to the radio before attempting to transmit.
Serious
damage to the radio can occur if transmitting without an antenna.
NOTE
First, test the sub-link of the base station to the first repeater or field station.
Initially treat the base station as the transmitting station and the first field or
repeater station as the receiving station. Disconnect the radio’s multicolored
cable from the RF modem. To start the test, have the person at the base station
initiate a radio transmission. When the radio transmission is received, if
squelch is broken, you will hear it on the speaker of the scanner. If you don’t
14-12
Содержание LoggerNet
Страница 2: ......
Страница 30: ...Preface What s New in LoggerNet 4 xxvi...
Страница 32: ...Section 1 System Requirements 1 2...
Страница 44: ...Section 2 Installation Operation and Backup Procedures 2 12...
Страница 136: ...Section 4 Setting up Datalogger Networks 4 80...
Страница 227: ...Section 7 Creating and Editing Datalogger Programs 7 9...
Страница 298: ...Section 7 Creating and Editing Datalogger Programs 7 80...
Страница 402: ...Section 9 Automating Tasks with Task Master 9 12...
Страница 406: ...Section 9 Automating Tasks with Task Master 9 16...
Страница 450: ...Section 11 Utilities Installed with LoggerNet Admin and LoggerNet Remote 11 22...
Страница 454: ...Section 12 Optional Client Applications Available for LoggerNet 12 4...
Страница 462: ...Section 13 Implementing Advanced Communications Links 13 8...
Страница 482: ...Section 14 Troubleshooting Guide 14 20...
Страница 570: ...Appendix F Calibration and Zeroing F 16...
Страница 578: ...Appendix G Importing Files into Excel G 8...
Страница 579: ......