DOCUMENT No.:
REVISION: 1.2
DATE: 2014/11/10
DC-MAM-001-X-C-2
Page 145
4.4.1.1
MAIN WHEEL FAIRING REMOVAL / INSTALLATION
TOOLS / EQUIPMENT REQUIRED
ITEM
QUANTITY
NOTES
1
3 mm Allen key / hex drive.
1
2
2.5 mm Allen key / hex drive.
1
The above list is not necessarily a complete list of all required tools and equipment needed. A calibrated torque
wrench (with adequate range) and the correct size (as implied by the above tool list) accessories (sockets etc.)
are implied for torqueing bolts / nuts, if applicable. Refer to paragraph 1.5 for torque values.
CONSUMABLE MATERIAL REQUIRED
ITEM
QUANTITY
NOTES
1
Loctite 222.
As needed.
Fairing screws.
2
Loctite 243
As needed.
Bolt retaining fairing to main axle spacer.
The above list is not necessarily a complete list of all material needed. Refer to the Sling 4 construction manual.
AUTHORISED PERSONNEL
Any person performing maintenance of any kind on the aircraft or any component thereof must do so in
accordance with national legislation. This is the responsibility of the aircraft owner and any person who is to
perform any maintenance on the aircraft.
Summary of Contents for Sling 4
Page 1: ......