Operation
122
Super-Vitesse CFS 3101, 3501 / Super-Vitesse CFS 3101 DO, 3501 DO 10.13
1. Press the
key once when being on
the bunker silo.
The following functions will be automatically
carried out one after the other:
Lift tailgate
Switch transport floor on when the
tailgate has reached its end position
The screen shows:
Switch Discharge mode A II on (Machine with dosing drums)
The
Discharge mode A II
is automatically switched off when the
tailgate is lowered.
During discharge, the transport floor feed can be switched on and off
as often as desired by pressing the
key.
Switch the p.t.o. shaft off to discharge step by step.
The dosing drums and the transport floor stop. The transport
floor automatically switches to standby mode and the "Feed On"
symbol is flashing.
1. Press the
key once when being on
the bunker silo.
The following functions will be automatically
carried out one after the other:
Lift tailgate until the set first opening
width is reached.
Switch gearboxes and clutches.
Switch transport floor to standby mode
when the tailgate has reached its set
first opening width. The "Feed on"
symbol is flashing.
The screen shows:
As soon as the p.t.o. shaft is switched
on, the dosing drums start to run and
after a short delay, the transport floor
automatically starts.
With the dosing drums powered,
the "Dosing drums On" symbol
appears.
With the transport floor powered,
the "Feed On" symbol is
permanently lit.