H/C demand, H/C changeover
10.1 Heat demand function
10.1.1 Purpose and enabling
The "Heat demand" function acquires heat demand from a heat distribution zone
via the bus. The collected heat requests can be routed to another zone
or
further
handled as a resulting setpoint condition (temperature request signal, heating flow
setpoint) as a continuous or digital signal.
Purpose
Contrl.
To enable function "Heat demand", assign the load signal of a controller, enable the
primary controller
or
assign output Q, d, Y, a.
Enabling
10.1.2 Use universal controller as consumer
Use "Extra configuration > Aggregates > Heat demand" at the corresponding
controller for a sequence of the controller to generate heat demand (see Section
10.3 for application examples).
Purpose
Contrl.
X
Main menu > Commissioning > Extra configuration > Aggregates > Heat demand >
Configuration
Operating line
Adjustable values / Comment
Controller 1
---, Sequence 1
Controller 2
---, Sequence 1
Controller 3
---, Sequence 1
This allows for generating a "Heat demand" signal that can be used by another
device on the KNX.
To do this, set a heat distribution zone.
Main menu > Commissioning > Communication > Distribution zones >
Operating line
Range
Factory setting
Heat distribution zone
1…31
1