Commissioning the system
Commissioning of the system will be carried out by OIPT in accordance with their
standard procedures and any additional requirements stated in the sales contract.
Generally, this will include the following items:
1)
Checking that the installation has been carried out satisfactorily.
2)
Powering up the system.
3)
Checking the operation of the system, including the Emergency Off facility and all
interlocks.
4)
Ensuring that the system can perform the processes specified in the sales contract.
5)
Providing training on the system.