Comparing results with the reference data on the transformer nominal plate, following
problems were detected:
-
problem on windings A
: Such huge difference could be due to a short
circuit on the winding. Additional measurements, like winding resistance
measurement and insulation test should be performed to define the root
cause.
-
problem on windings C
: turn ratio was not calculated, so this is direct
point to open circuit (broken connection). We also propose, to perform
additional winding resistance measurement in such case.
Exercise 3:
Setup switch Nm. 4 to position 3:
Method used
Simulated condition
Expected result
r
A
= 10.106
Ω,
∆
r = 0.31%, @ Uex =80V, fex= 70 Hz
r
B
= 10.089
Ω,
∆
r = 0.14%, @ Uex =80V, fex= 70 Hz
r
C
= > 8000
Ω,
∆
r = >100%, @ Uex =80V, fex= 70 Hz
Table 58-3: Transformer turn ratio measuring setup/result presentation with simulated error
Start the measurement by pressing START key
on the instrument or icon
on the LCD
Expected result:
Summary of Contents for MI 3298
Page 55: ...Power Network Application Trainer Earthing Grounding network impedance measurement 55 ...
Page 56: ...Power Network Application Trainer Earthing Grounding network impedance measurement 56 ...
Page 124: ...Power Network Application Trainer Earthing Grounding network impedance measurement 124 ...
Page 228: ...MI 3290 Earth Analyser 228 ...
Page 229: ...MI 3280 Digital Transformer Analyser 229 ...
Page 230: ...MI 3280 Digital Transformer Analyser 230 ...
Page 231: ...MI 3250 MicroOhm 10A 231 ...
Page 232: ...MI 3205 TeraOhmXA 5kV 232 ...