4.2.2 Step voltage measurement with Step/Contact instrument MI
3295S and MI 3295M
Instrument used for current generation: MI 3295S
Instrument used for step voltage measurement: MI 3295M
Figure 84-2: Step voltage setup with MI 3295S
Note:
MI3295S could generate maximal current of 55 A, so it is intended for
measurement bigger objects (comparing to MI 3290).
MI3295M is used in this application as Volt-
meter with internal resistance of 1 kΩ
(simulation of human body resistance).
Generated current is limited with the design of MI 3298 P1.
Connect MI3295S
only to training module terminals which are indicated in this manual.
Switch position
Simulated
condition
Applications
Expected result
Industrial areas
Transformer stations
Radio towers
Pylons with/without
protective earth cable
connection
Solar power plants
Wind & water turbine
Related to the position of
test probes.
Table 48-2: Step voltage measuring method setup/result presentation
MI 3295S instrument:
1. Before starting measurements, synchronize the time and date on the Volt-meter MI
3295M and station MI 3295S. The main purpose of the Time/ Current
synchronization is to enable a correction of the step and contact voltage results after
Summary of Contents for MI 3298
Page 55: ...Power Network Application Trainer Earthing Grounding network impedance measurement 55 ...
Page 56: ...Power Network Application Trainer Earthing Grounding network impedance measurement 56 ...
Page 124: ...Power Network Application Trainer Earthing Grounding network impedance measurement 124 ...
Page 228: ...MI 3290 Earth Analyser 228 ...
Page 229: ...MI 3280 Digital Transformer Analyser 229 ...
Page 230: ...MI 3280 Digital Transformer Analyser 230 ...
Page 231: ...MI 3250 MicroOhm 10A 231 ...
Page 232: ...MI 3205 TeraOhmXA 5kV 232 ...