1-2
Issue 1
November 1998
363-208-010, Appendix 1
NJ00675A-2 Dual Power Feed Unit Installation Procedure
Support
If any of the steps specified in this procedure cannot be completed as indicated,
call the next level of support or the Lucent Technologies Regional Technical Assis-
tance Center (RTAC) by the following phone number for assistance.
RTAC: 1-800-CAL RTAC (225-7822)
Training
No specific training is required.
Time Estimates
a. Overall time to perform this procedure is estimated to be one hour.
b. There will be no time out-of-service during this procedure.
c. One installer or craftsperson is recommended for this procedure.
Risk Assessment
Procedural Risk Assessment (DPFU added out of
service)
Rating:
LOW
Since the DPFU is to be installed prior to service turn-up this procedure
has a LOW procedural risk rating, since there is NO potential for a service
interruption to the end customer, if any procedural deviations or
procedure specific equipment failures occur during the procedure.
Procedural Risk Assessment (replacing or “hot
swapping” a defective DPFU)
Rating:
LOW
Since the DPFU cabling is designed to facilitate this procedure on an in-
service system this procedure has a LOW procedural risk rating, since
there is low potential for a service interruption to the end customer, if any
procedural deviations or procedure specific equipment failures occur
Summary of Contents for SLC-2000 Access System Central Office Terminal
Page 1: ...SLC 2000 Access System Customer Assembly Manual for RT Frames 363 208 010 Issue 5 May 1997...
Page 4: ...This page is intentionally blank...
Page 10: ...viii Issue 5 May 1997 Contents...
Page 16: ...xiv Issue 5 May 1997 Tables...
Page 24: ...1 ii Issue 5 May 1997 Contents General Information...
Page 34: ...2 iv Issue 5 May 1997 Tables Installation Procedures 2 1 Dimensions for Figure 2 2 6...
Page 66: ...3 viii Issue 5 May 1997 Contents Cabling Wiring and Assembly...