1. Carefully place the Power Supplies in the slots in the Rack.
2. Make sure that the connector at the back seats properly. Insert a
flat blade in the slots at the top and bottom of the power supply
cover while pulling backward to open the cover.
3. Fasten the screws (located in the face of the power supply) into
the tabs at the top and bottom of the rack. Set the Torque to 0.4 -
0.5 N.m (3.5 - 4.4 Lb-In). See the following figure for power supply
mounting details.
70
Summary of Contents for ControlEdge 900 platform
Page 6: ...6 Contents ...
Page 12: ...12 Chapter 1 About this guide ...
Page 52: ...52 ...
Page 57: ...57 One Slot Rack 1 CPM 1 EPM 1 P S 1 RM ...
Page 59: ...59 One Slot Rack ...
Page 62: ...Figure 5 7 Rack dimensions with redundant power supply 62 ...
Page 75: ...75 c Insert the Ethernet cables and mount the security cover for the EMP ...
Page 76: ...d Optional mount a wire security seal The user should get a wire security seal themselves 76 ...
Page 124: ...Figure 5 31 Universal Analog Input Wiring Figure 5 32 Examples of RTD Input Wiring 124 ...
Page 137: ...137 Figure 5 47 Pulse Outing Wiring Figure 5 48 Frequency Wiring ...
Page 144: ...Figure 5 57 16 point High Level Analog Input Wiring 144 ...
Page 147: ...147 Figure 5 60 AC DC Isolated Input Module Wiring ...
Page 148: ...148 ...
Page 168: ...168 ...
Page 178: ...178 Chapter 8 Diagnostics and Troubleshooting ...
Page 222: ...Appendix A Installing RTP 222 ...
Page 227: ...Appendix A Installing RTP Relay Output RTP Internal schematic 227 ...