CHAPTER 3 COMMISSIONING OPERATION
PART 1 SECURITY REQUIREMENTS
1 PRECAUTIONS FOR CONSTRUCTION
All commissioning and maintenance personnel must learn and strictly comply with construction
security specifications. Security measures must be taken especially for outdoor operations.
Workers of special types of labor, such as refrigerating engineers, electricians, and welders, must
have professional certificates. No worker is allowed to do another type of labor.
The equipment must be powered off before relevant operations, and other security requirements
should be strictly complied with.
All installation and maintenance operations must comply with design requirements of this product and
national and local security operation requirements. Rule-breaking operations are prohibited.
2 PRECAUTIONS FOR THE USE OF REFRIGERANTS
The Ultra Heat GMV serial unit is a refrigerating system of R410A working substances. Pay
attention to the following points:
The refrigerating system of R410A working substances has a higher working pressure than that of R22
working substances. The working pressure of the former is 1.6 times than that of the latter.
The refrigerating system of R410A working substances uses thicker-walled copper tubes than that of
R22 working substances. Adopt copper tubes with appropriate wall thickness.
R410A working substances are azeotropic mixture working substances. Refrigerants must be
appended in the form of liquid.
3 FUNCTION SETTINGS OF ODUS
Function application of ODUs consists of function DIP switch settings and function button settings,
including special engineering requirements.
Summary of Contents for Ultra Heat GMV-V72W/A-F
Page 1: ...Ultra Heat GMV Multi VRF TECHNICAL SERVICE MANUAL R410A Heat Pump Series...
Page 22: ...Ultra Heat GMV VRF Technical Service Manual INSTALLATION 17 CHAPTER 2 INSTALLATION...
Page 26: ...Ultra Heat GMV VRF Technical Service Manual INSTALLATION 21...
Page 105: ...Ultra Heat GMV VRF Technical Service Manual MAINTENANCE 100 CHAPTER 4 MAINTENANCE...
Page 116: ...Ultra Heat GMV VRF Technical Service Manual MAINTENANCE 111...
Page 180: ...Ultra Heat GMV VRF Technical Service Manual REMOTE CONTROL 175 CHAPTER 5 REMOTE CONTROL...
Page 206: ...Ultra Heat GMV VRF Technical Service Manual REMOTE CONTROL 201...
Page 239: ......
Page 240: ...Jf00303483...