Generic Procedure
The test verifies the isolation of the power line from the chassis.
The testing meter is connected from accessible metal parts of the case to ground.
Measurements should be made under the test conditions specified in:
•
Table 10-9 on page 10-11
•
Table 10-10 on page 10-11. Record the highest reading of current.
1.) Connect Safety analyzer to wall AC power outlet.
2.) Plug the equipment under test power cable into the receptacle on the panel of the meter.
3.) Connect the meter to an accessible metal surface of the scanner using the cable provided with
the meter.
4.) Select the Chassis or Enclosure leakage function on the meter.
NOTE:
Consult the manufacturer’s user manual of the Safety Analyzer.
5.) Test opening and closing the ground with the scanner on and off as indicated in
Table 10-9
or
Table 10-10
as applicable.
NOTE:
Consult the manufacturer’s user manual of the Safety Analyzer that will be used to perform the tests.
The maximum allowable limit for chassis source leakage is shown in:
•
Table 10-9 on page 10-11
•
Table 10-10 on page 10-11
as Chassis/Enclosure Leakage.
Summary of Contents for 5205000
Page 1: ...10 20 14 GEHC_FRNT_CVR FM LOGIQ E9 SERVICE MANUAL Part Number 5535208 100 Revision Rev 2 ...
Page 2: ......
Page 21: ...GE DIRECTION 5535208 100 REV 2 LOGIQ E9 SERVICE MANUAL 19 ZH CN KO ...
Page 807: ......
Page 808: ......