Equipment Installation
XDM-300 Installation and
Maintenance Manual
3-22 ECI
Telecom
Ltd.
Proprietary
417006-2311-0H3-A00
7.
Route each shelf power cable along the rack side rails down to the
corresponding shelf position, then securely attach the power cable to the
rack inner wall using cable ties. Attach a tag to each power connector in
accordance with its function.
N
OTE
:
Connect the cables to the shelves only after
completing the installation of the shelves and all other
components.
To install the xRAP-B circuit breakers:
1.
If the xRAP-B front panel has not been removed, open the two captive
screws fastening the xRAP-B front cover to its chassis and remove the
cover (see the following figure).
Figure
3-12: Installation of xRAP-B circuit breakers
2.
Identify the circuit breaker corresponding to the power circuit A of shelf 1
(the circuit breaker is included in the installation parts kit supplied with the
equipment); its rating is in accordance with the ordered shelf configuration.
The recommended circuit breakers according to the XDM-300 shelf
configuration are listed in the following table.