Equipment Installation
XDM-300 Installation and
Maintenance Manual
3-4 ECI
Telecom
Ltd.
Proprietary
417006-2311-0H3-A00
Depending on the specific equipment being installed according to the site
installation plan, the installation of an XDM-300 system comprises the general
stages in the order of execution set out in the following table.
Table
3-1: Outline of horizontal XDM-300 installation sequence
Step Procedure
Section
1.
Install a rack (if required).
)
2.
Unpack and perform a visual inspection.
Unpacking and Visual
Inspection (on page
)
3.
Install ancillary equipment in the rack,
including:
|
xRAP-B, xRAP-100, or xRAP
|
Cable guides (two)
|
Cable slack tray
|
Fiber guides for ETSI A racks (two)
|
FST) (optional)
|
ODF units (optional)
|
Optical Patch Panel (OPP)
Note:
Installation of the optional
xDDF-21 channel patch panel is
implemented as part of the traffic cable
routing process.
Installing Ancillary Units in
Racks (on page
)
4.
Install the XDM-300 shelf in the rack.
Note:
If your site installation plan
includes TPU protection, the XDM-300 is
supplied with the TPU already installed.
If you need to connect a TPU unit to an
existing XDM-300 shelf, see Attaching
TPUs/OCU to the XDM-300 Shelf (on
page
).
Installing the Shelf in the Rack
(on page
5.
Install the air filter.
Installing the Air Filter
6.
Install the common cards in the
XDM-300 shelf, including:
|
FCU300
|
ECU300/ECU300-F
|
MXC300 with NVM flash card