Equipment Installation
XDM-300 Installation and
Maintenance Manual
3-30 ECI
Telecom
Ltd.
Proprietary
417006-2311-0H3-A00
Installing the xRAP-100 circuit breakers
To install the xRAP-100 circuit breakers:
1.
If the xRAP-100 front panel has not been removed, open the two captive
screws fastening the xRAP-100 front cover to its chassis and remove the
cover (see the following figure).
Figure
3-17: Installation of xRAP-100 circuit breakers
2.
Identify the circuit breaker corresponding to the power circuit A of shelf 1
(the circuit breaker is included in the installation parts kit supplied with the
equipment); its rating is in accordance with the ordered shelf configuration.
The recommended circuit breakers according to the XDM-300 shelf
configuration are listed in the following table.
3.
Insert the circuit breaker into the circuit breaker sockets located on the
xRAP-100 source A power terminal board, as shown in the previous figure.
4.
If more than one shelf is powered from source A, repeat Steps 2 and 3 to
insert the other circuit breaker into the corresponding shelf position of the
power terminal board.
5.
If an additional power source is used, repeat Steps 2, 3, and 4 for source B
circuit breakers.