PG7000™ OPERATION AND MAINTENANCE MANUAL
© 1998-2008 DH Instruments, a Fluke Company
Page 24
and setting up PG7000 to use an automated pressure generation/control
component (see Section 3.9.9).
If an AMH automated mass handling system is being used, set up the AMH
mass set and the AMH mass handler following the instructions in the AMH-
38/AMH-100 Operation and Maintenance Manual.
Level the platform using the PG7000 Platform’s two front leveling feet and
the level mounted on the front of the platform. (Or on the optional AMH mass
handling system.)
2.3.1.2
SYSTEM PRESSURE INTERCONNECTIONS
Interconnect the PG7000 Platform, pressure generation/control components and
a test connection.
The pressure connection on the PG7000 TEST port is:
•
PG7102/PG7601:
DH200 (DH200 is equivalent to AE SF250C,HIP LF4,
etc.). Adapters to convert the DH200 connection to 1/8 in. NPT female and
1/8 in. swage are provided with PG7102 and PG7601 Platform accessories.
•
PG7202:
DH500 (DH500 is equivalent to AE F250C, HIP HF4, etc.).
Connect the gas test medium pressure control/generation component to the
TEST port. If the PG7202 is to be operated in oil, connect the oil pressure
control/generation component to the DRAIN port (the gas or oil component is
disconnected when not in use, see Section 2.3.3).
•
PG7302:
DH500 (DH500 is equivalent to AE F250C, HIP HF4, etc.).
If using a standard interconnections kit such as PK-7600-PPC/MPC P/N 400985,
PK-7600-PPC/MPC-DIF P/N 401581 or PK-7100-MPCD-DIF P/N 401645, see the
instruction sheet provided with the kit for installation instructions. If an OPG1 or
GPC1 generator/controller is being used, pressure interconnecting hardware is included
with it. See its Operation and Maintenance Manual for connection instructions.
2.3.1.3
SETTING UP A MASS SET
If installing an MS-AMH-xxx mass set for use with an AMH automated mass
handling system, see the AMH-38/AMH-100 Operation and Maintenance Manual.
To install a PG7000 manual mass set, place the mass loading tray (provided with
the mass set accessories) at the desired location then install the individual
masses on the mass loading tray. See the AMH-38/AMH-100 Operation and
Maintenance Manual for instructions on installation of an AMH mass set for
automated mass handling.
It is VERY IMPORTANT that the individual masses be installed on the mass
loading tray in proper sequence. This will ensure that PG7000 mass loading
instructions are executed properly (carefully follow the instructions provided in
Section 2.3.1.3, Installing Masses on the Mass Loading Tray).
Installing Masses on the Mass Loading Tray (Manual Mass Set)
PG7000 masses are shipped in reusable, molded shipping and storage cases.
One of the cases contains a 4.0, 4.5 or 5 kg mass and the masses of 2 kg and