Appendix
82
Flame tube
Is the flame tube placed correctly?
Combustion chamber
cover
Are the adjusting screws for the increasing of the flue gas
temperature adjusted correctly?
Flue gas connection
Is a chimney draft regulator, barometric damper implemented?
Airation/boiler room
Does the boiler room have required make-up air?
Nameplate
Is the nameplate placed on the boiler?
Electric installation and regulation
Power supply
Check the electrical connection? (terminal box)
Check the dimensions of the fuses.
Settings-Boiler control
unit
Are the settings of the boiler control unit according to the
installation manual?
Settings-Heating
controller
Set the parameters, the heating circuit program and domestic
hot water program.
Boiler sensor
Securing location and connection –
Cable routing
Hydraulic Connection
Circuit pumps
Check the switch on temperature (min. 140°F ) for boiler
controlled pump (Parameter P 281).
Low Water Cut Off
Is a low water cut off installed? (terminal box)
Test low water device
Boiler connection
Is the pellet boiler correctly connected
Is the hydraulic system free of air?
Is the system filled up with water?
Check the pressure.
Safety systems
Fire protection - ball
valve
Check the function?
Safety temp. sensor
Check the installation and explain the function.
Securing location and connection –
Cable routing
Negativ draft control
Check the function.
Safety valve
Is a safety valve installed?
Emergency stop switch
Is there an emergency stop switch?
Fire extinguisher
Is there a fire extinguisher?
Instruction
Heating-up
Explanation of functions, malfunctions and maintenance to the
customer.
Heating controller
Explanation of the heating controller.
Operating manual
Explanation of the operating and maintenance regulations to the
customer.
Maintenance contract
Notice to the legal regulations;
Date:
______________________________________
Signature authorizied technician:
Signature customer:
____________________________________________
____________________________________________
The customer confirmes that he got enough information about operation and maintenance of the heating plant.
Installation Manual PES 36–56
PE 3671 USA 2.3
Содержание Pellematic PES 12-20
Страница 38: ...Connecting up to the power supply 38 Installation Manual PES 36 56 PE 3671 USA 2 3...
Страница 46: ...Connecting up to the power supply 46 Installation Manual PES 36 56 PE 3671 USA 2 3...
Страница 47: ...Connecting up to the power supply 47 PE 3671 USA 2 3 Installation Manual PES 36 56...
Страница 52: ...Operating the pellet boiler 52 Setting date and time Installation Manual PES 36 56 PE 3671 USA 2 3...
Страница 88: ...Appendix 88 Installation Manual PES 36 56 PE 3671 USA 2 3...
Страница 92: ...Appendix 92 Installation Manual PES 36 56 PE 3671 USA 2 3...
Страница 99: ...Appendix 99 Labeling 105x74 PE 3671 USA 2 3 Installation Manual PES 36 56...
Страница 100: ......