Commissioning
Aperion 2101, Aperion 2401, Aperion 3401 04.18
109
9.
Use the four connecting screws (4), two on
each side, to screw the beaters.
Fig. 70
10.
Mount the chains (5).
11.
Mount the chain tensioners (6).
Fig. 71
5.13.2
Remove beaters
1.
Secure the machine against accidental rolling if it is not hitched up to the tractor.
2.
Secure tractor and machine against accidental starting and rolling if they are coupled to each
other.
3.
Open the tailgate and secure it against accidental lowering.
4.
For removal, align the dosing unit mount for pallet fork (72207602) (1) with the bottom locating
boreholes of the beaters by means of a forklift.
5.
Screw the four boreholes (2) in the dosing unit mount for pallet fork (1) to the locating boreholes
of the beaters.
6.
Open the guards (3).
7.
Remove the chain tensioners (6).
8.
Remove the chains (5)
9.
Unscrew the four connecting screws (4), two on each side, and fold them out.
10.
Now use a forklift to lift the beaters from the machine.
11.
Mount the side elements.
Summary of Contents for Aperion 2101
Page 2: ......
Page 42: ...Product description 42 Aperion 2101 Aperion 2401 Aperion 3401 04 18 Fig 36...
Page 44: ...Product description 44 Aperion 2101 Aperion 2401 Aperion 3401 04 18 Tyre pressures with 26 5...
Page 176: ...Circuit diagrams 176 Aperion 2101 Aperion 2401 Aperion 3401 04 18 Chassis of Aperion Fig 131...
Page 182: ...Circuit diagrams 182 Aperion 2101 Aperion 2401 Aperion 3401 04 18 Chassis of Aperion Fig 135...
Page 186: ...Circuit diagrams 186 Aperion 2101 Aperion 2401 Aperion 3401 04 18 Circuit diagram Fig 137...
Page 190: ...Circuit diagrams 190 Aperion 2101 Aperion 2401 Aperion 3401 04 18 Circuit diagram Fig 139...
Page 196: ...Index 196 Aperion 2101 Aperion 2401 Aperion 3401 04 18...