1 Prerequisites and Visual Inspection
1.1 Prerequisites
1
Prerequisites and Visual Inspection
1.1
Prerequisites
The following prerequisites must be fulfilled prior to initial start-up:
•
Electrical and mechanical installation of the machine must have been completed and the
axes prepared for operation.
The following points must be confirmed by the customer!
•
Customer PLC program operational and pretested.
•
Measuring system installed and wired as far as SINUMERIK.
•
Cables connected to the machine. Cable shields run to the control neutral point as per
Interface Description. Flexible earth wires installed. Earthing concept observed (inspect
carefully!).
•
Customer personnel support for work on the interface unit, work on the machine, machine
operation and customer produced PLC program.
Recommendation:
Prelimit travel ranges (greater clearance distances) by displacing the end stop
(EMERGENCY STOP cam).
•
The specified machine data is available.
•
Data carriers are available for checking machine specific functions.
1.2
Visual inspection
General remarks:
Refer to the "EMC Guidelines", Order No. 6FC 3987-7DB
These guidelines provide the following information:
•
Why are EMC guidelines necessary?
•
What external interference sources affect the control?
•
How can interference be prevented?
•
Practical examples for an interference free installation.
•
How should electronically endangered components (EEC) be handled?
•
How can an EMC problem be rectified?
•
What standards are relevant to EMC?
© Siemens AG 1992 All Rights Reserved 6FC5197- AA50
1–1
SINUMERIK 840C (IA)