Figure 3-17 Installing side panels 1
(1) Side panels
●
If a power supply and distribution equipment cabinet is located at the end of
a row and an IT cabinet at the head of a row, install side panels only on the
outer side of the head cabinet.
Figure 3-18 Installing side panel 2
(1) Side panel
Preparations
Tools: Phillips screwdriver, flat-head screwdriver
Material: side panel
Procedure
Step 1 Install the floating nuts.