No.
Check Item
Check Result
3
There is no foreign matter such as adhesive tape,
cable ties, paper, or packing materials left in and
around the aisle.
□ Passed □ Failed
Cable Installation Checklist
No.
Check Item
Check Result
1
All cable joints are secured properly, especially the
cable joints of network cables and cables inside
cabinets.
□ Passed □ Failed
2
Exposed parts of cables and cable lugs near the
cable terminals are wrapped with insulation tape
or heat-shrink tubing.
□ Passed □ Failed
3
All wiring terminals are securely installed with flat
washers and spring washers and are in good
contact.
□ Passed □ Failed
4
Cables are bound neatly, and cable ties are
secured evenly and properly in the same direction.
□ Passed □ Failed
5
Cables are routed in a way convenient for
maintenance and future capacity expansion.
□ Passed □ Failed
6
All labels at the cable ends are clear.
□ Passed □ Failed
7
Excess sections of cable ties are neatly cut.
□ Passed □ Failed
8
There is no unnecessary adhesive tape or cable tie
on cables.
□ Passed □ Failed
Electric Installation Checklist
No.
Check Item
Check Result
1
All ground cables are copper cables with
diameters meeting the requirements. No switch or
fuse is installed on a ground cable, and no open
circuit occurs.
□ Passed □ Failed
2
All PE cables, AC input cables, and intra-cabinet
cables are connected correctly according to the
power system circuit diagram, and all screws are
fastened. The input and output cables are not
short-circuited.
□ Passed □ Failed
FusionModule2000-S Smart Modular Data Center
User Manual
7 Appendix
Issue 03 (2021-07-15)
Copyright © Huawei Technologies Co., Ltd.
275