Power-On Commissioning
5.1 Power-On Commissioning for the Cooling System
For details about the power-on commissioning for the cooling system, see the
NetCol5000-A050 In-Row Air Cooled Smart Cooling Product User Manual (1350
mm Depth)
and
NetCol5000-A050 In-Row Air Cooled Smart Cooling Product
Quick Guide (1350 mm Depth)
.
5.2 Power-On Commissioning for the Power Supply and
Distribution System
5.2.1 Powering On the System (Integrated UPS)
5.2.1.1 (Optional) Commissioning the ATS Before Power-On
Context
CA UTION
Perform system commissioning and power-on strictly according to the system
manual and ATS instructions. For any changes in operations and parameters,
consult Huawei engineers. Otherwise, system commissioning or power-on may
fail, or even the cabinet is damaged.
Procedure
Step 1 Switch on all SPD circuit breakers in the integrated UPS.
Step 2 Switch on the upstream power input circuit breaker for the integrated UPS to
power on the UPS cabinet. If the Power indicator in the upper part of the
integrated UPS lights up, the UPS cabinet is powered on properly.
FusionModule2000-S Smart Modular Data Center
User Manual
5 Power-On Commissioning
Issue 03 (2021-07-15)
Copyright © Huawei Technologies Co., Ltd.
119