Procedure
Step 1 Install cabinet electronic clasp lock cables according to the cabinet electronic clasp
lock layout.
1. Cascade the cabinet electronic clasp locks of odd- and even-numbered
cabinets hand-in-hand respectively.
2. Connect one end of the network cable to the RS485_IN port on the electronic
clasp lock of the first cabinet among odd-numbered cabinets, and the other
end to the COM2 port on the ECC800-Pro.
3. Connect one end of another network cable to the RS485_IN port on the
electronic clasp lock of the first cabinet among even-numbered cabinets, and
the other end to the COM3 port on the ECC800-Pro.
Figure 4-18 Installing cabinet electronic clasp lock cables
----End
4.5 Routing Power Cables for the PAD and WiFi Module
Prerequisites
The PAD and PAD power cable have been installed.
Context
NO TE
The PAD is installed at the end of a row. When the PDF is deployed inside the row, the PAD
power cable needs to be connected to the PAD through the PDF.
Procedure
Step 1 Connect the PAD and WiFi module to the USB port on the ECC800-Pro using a 2.8
m one-to-two cable. The following figure shows the cabling routes.