10. Installation check and Test operation
10.1 Installation check
Carefully explain the operation method to the customer using the manual.
Before starting the HP unit, check each item in the list below and put a tick mark in the .
Locations and positioning
The vibration damping feet are fitted
The unit is fixed to the surface it rests on
Maintenance clearance comply with the specifications in the manual
The position of the outdoor air temperature probe complies with the information of the manual
The position of the room air temperature probe (Remote controller) complies with the information of the
manual
The position of the DHW tank probe complies with the information of the manual
All safety conditions have been respected
Water circuit piping and appliances
Water connections have been carried out as per the information in the manual
All water connections are tight
The water line filter is installed on the HP inlet as close as possible to the HP unit and in a position that is
easy to access for maintenance
The water line filter is installed on the DHW tank Inlet/Outlet as close as possible to the HP unit and in a
position that is easy to access for maintenance
The pressure gauges with a suitable scale are installed on the Inlet and outlet of water circuit
The flow switch is installed on the outlet of water circuit and is electrically connected
The connection pipes are suitably supported so that these do not weigh on the appliance
The expansion vessel and safety valve installed on the DHW circuit and suitably-sized
The expansion vessel is installed on the water circuit and suitably-sized
The low-loss header is installed if the water content is insufficient
Make sure the water circuit has been washed and drained
The air vent valves are installed at the highest points in the system
There is no air in the system (vent if necessary)
The shut off valves are installed on the Inlet/Outlet of system circuit and DHW circuit
The drain valves are installed at the lowest points in the system
The vibration damper joints are installed on the Inlet/Outlet of system circuit
The system water content complies with the specifications in the manual
The DHW Electric heater has been installed in DHW tank for Legionella prevention
Suitable water flow rate for operation of the entire unit is guaranteed as specified in the manual
All pipes are insulated with suitable vapour barrier material to prevent formation of condensation and heat
loss, with control and shut-off devices protruding from the insulation
Electrical connections
All electrical connections are tight
Electrical connections have been carried out correctly
Voltage is within a tolerance of 10% of the rated voltage for the HP unit
Power supply electrical complies with the data on the rating plate and specified in the manual
The earth wires connected securely