4.17 Adjust the Tension Arm of the Wrapping Ring
Before starting the procedure
Yearly and when necessary check and adjust the tension of the wrapping ring tension arm.
Procedure
1.
Make sure that the machine is "OFF". Refer
to the shutdown procedure for maintenance.
2.
Adjust the nut (1) on the eyebolt until the
spring (2) extends to 90 mm.
GUID-67AFBC3B-7C49-4CAE-93CA-5ADF2ED39A01-high.jpg [High]
Fig. 25
(1)
Nut.
(2)
Spring.
(3)
Wrapping Ring.
GUID-D6648C64-BD68-4FDB-8595-B90EA8D7BC04-high.jpg [High]
Fig. 26
(A)
90 mm.
GUID-3DBB63B7-0317-4151-AC21-DD585860D40D [V1]
4. Maintenance and Lubrication
138
Baler Wrapper Combination
4900.LE.EN01
Summary of Contents for LELY RPC 130 F
Page 2: ......
Page 8: ...Table of contents 8 Baler Wrapper Combination 4900 LE EN01...
Page 32: ...1 Safety 32 Baler Wrapper Combination 4900 LE EN01...
Page 34: ...Table of contents 34 Baler Wrapper Combination 4900 LE EN01...
Page 110: ...3 Operation 110 Baler Wrapper Combination 4900 LE EN01...
Page 112: ...Table of contents 112 Baler Wrapper Combination 4900 LE EN01...
Page 122: ...Danger Zones page 31 4 Maintenance and Lubrication 122 Baler Wrapper Combination 4900 LE EN01...
Page 148: ...Table of contents 148 Baler Wrapper Combination 4900 LE EN01...
Page 158: ...Table of contents 158 Baler Wrapper Combination 4900 LE EN01...
Page 164: ...6 Specifications 164 Baler Wrapper Combination 4900 LE EN01...
Page 167: ......
Page 168: ...AGCO Corporation 2018 All rights reserved 4900 LE EN01 English May 2018...