Installation manual of system “bp408” - Commissioning
Is the wire cross-section chosen according to the power consumption of the lift?
Yes
□
If a fuse switch is available, are the permissible fuse links fitted?
Yes
□
Is the automatic circuit breaker for the control voltage switched off?
Yes
□
Is the circuit breaker for the safety circuit switched off?
Yes
□
Are the supply lines correctly secured?
Yes
□
If a high-speed brake excitation is available, are the circuit breakers switched on?
Yes
□
The motor protection switches, overcurrent releases,
Residual Current-operated protective Device (RCD) circuit breakers , phase monitors,
etc. installed in the control system can only be preset by
Böhnke + Partner GmbH and must be adapted to the connected equipment during
commissioning by you
.
Have you made the adjustments?
Yes
□
Are all protective conductors connected correctly?
Yes
□
Have you followed all the interference suppression measures and EMC instructions of
the inverter manufacturer?
Yes
□
Did you follow the commissioning instructions of the control system and the drive?
Yes
□
Is the return control switched on?
Yes
□
If you have responded to all questions with »Yes«, then you may switch on the
mains voltage in compliance with the following chapters.
Содержание bp408
Страница 2: ......
Страница 24: ...24 Installation manual of system bp408 Safety instructions...
Страница 52: ...52 Installation manual of system bp408 The control system bp408...
Страница 58: ...58 Installation manual of system bp408 Installation and assembly...
Страница 80: ...80 Installation manual of system bp408 Electrical connection...
Страница 118: ...Installation manual of system bp408 Appendix 118 Appendix A Menu navigation bp408...
Страница 119: ...119 Installation manual of system bp408 Appendix B Update of the firmware via USB stick...