8.11 Commissioning the machine
Checking the controller settings
Section
Confirmed?
➤ Language correctly set?
➤ Date and time correctly set?
➤ Display format correctly set?
➤ OFC/SFC: Operating mode correctly set?
Tab. 84 Check list for starting the machine
1. Check and confirm all the items in the check list before first start-up of the machine.
When power is applied to the machine the controller boots and carries out a self test.
The display and the
Controller on LED illuminate.
The actual working pressure, the time and the airend discharge temperature are displayed in
the first line of the display.
The operating mode is mapped as a pipe and instrument diagram on the display.
Fig. 32 Operating mode
2. Continue the commissioning process as described in chapter "Commissioning" of the ma‐
chine's operating manual.
8
Initial Start-up
8.11 Commissioning the machine
No.: 901700 14 E
Service Manual Controller
SIGMA CONTROL 2 BLOWER ≥ 4.0.X
135
Содержание SIGMA CONTROL 2
Страница 2: ...KKW SSC 2 15 en IBA SIGMA CONTROL BLOWER KKW SSC 2 15 20220810 080650...
Страница 8: ...List of Illustrations vi Service Manual Controller SIGMA CONTROL 2 BLOWER 4 0 X No 901700 14 E...
Страница 12: ...List of Tables x Service Manual Controller SIGMA CONTROL 2 BLOWER 4 0 X No 901700 14 E...