Locating the Discharge Opening
What You Should Know
The last bolt hole in the chute should line up with the center of the discharge opening, that is to be cut.
With this last bolt hole as reference, it is possible to approximate an opening.
1. Use the chute bolt hole and mark the horizontal center. Measure approximately 9-1/2" above and
below the horizontal center and mark the horizontal cut lines.
2. Mark the vertical center by measuring over 11" from the right or left chute bolt holes. Then from the
vertical center, measure approximately 7" on both sides and mark the vertical cut lines.
3. Cut an opening where marked, making sure that corners have a minimum of 1-1/2" radius.
Figure 9-18
Locating the discharge opening
57
5
th
ring sidewall sheet from the base
PNEG-5490D-2X
90' Diameter EVO-50 Beam 2X Bin
213
Содержание EVO-50
Страница 6: ...NOTES 6 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Страница 34: ...NOTES 34 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Страница 130: ...NOTES 130 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Страница 188: ...NOTES 188 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Страница 220: ...NOTES 220 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...