• 1/2" Drive impact socket set
• Lifting jacks
• Center pole roof support
• Step ladders
• Large C-clamp or welding V-grip for clamping
NOTE:
Quantities required will depend on the number of workers and size of the bin.
Guidelines for Proper Storage of Grain Bin Materials Prior to
Construction
Storage of the build materials prior to construction is important. Do not to allow moisture to remain
between sheets or panels.
• Wet storage stain (rust) will develop when closely packed bundles of galvanized material, such as
sidewall and roof sheets, have moisture present. Inspect roof and sidewall bundles on arrival for any
moisture. If moisture is present, it must not be allowed to remain between the sheets. Separate the
sheets or panels immediately and wipe them down. Spray with a light oil or diesel fuel.
• If possible, sidewall bundles, roof sheets and other closely packed galvanized materials should be
stored in a dry, climate controlled building. If outdoor storage is unavoidable, the materials should be
stored so that they are raised above the ground and vegetation. Any stacking and spacing materials
should not be corrosive or wet. Be sure to protect materials from the weather, but permit air
movement around the bundles if possible.
• Storing roof bundles and sidewall sheets at a slight incline can also help minimize the presence of
moisture. Storing the bundles with the center of the dome up (like an arch) is one option for
minimizing moisture during storage. Sidewall bundles can also be stored on edge but must be
secured so that they do not fall over and cause injury.
• If “white rust” or “wet storage stain” occurs, contact the manufacturer immediately about ways to
minimize the adverse effect upon the galvanized coating.
Overview for a Typical Bin Installation
These are the typical steps one would perform when constructing a grain bin. Procedures may vary
depending on the site requirements.
Pre-Assembly Activities
• Sorting and grouping parts.
• Install the wind ring bracket to the stiffeners.
• Assemble the rafter clips to rafters on the ground.
• Assemble the A-frames.
• Assemble the center collar.
• Install the vent to the roof panels.
18
PNEG-5490D-2X
90' Diameter EVO-50 Beam 2X Bin
Содержание EVO-50
Страница 6: ...NOTES 6 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Страница 34: ...NOTES 34 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Страница 130: ...NOTES 130 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Страница 188: ...NOTES 188 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Страница 220: ...NOTES 220 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...