Heating system servicing
Logano plus GB312 - Technical specifications are subject to change without prior notice
61
V
Press the
button to open the
BOILER/BURNER
menu.
The monitor readings are displayed as a list, i.e. turning
the selector scrolls down to more readings.
V
Press the
button to increase the boiler output to a
higher percentage.
V
Read off output on RC35.
V
Wait until output reaches 100%.
V
Read off differential pressure from the tester and com-
pare with the levels shown in Table 15.
If the differential pressure measured is higher than the
figure in the table, the heat exchanger must be cleaned
using either the dry or wet method.
V
Remove differential pressure tester from burner pres-
sure testing nipple and pressure testing point on flue
socket
V
Seal the testing point on the flue pipe.
V
Remove the pressure testing nipple from the burner
and carefully refit, seal and tighten the blanking plug.
9.6.2
Cleaning the burner and heat exchanger
V
Shut down the heating system (
Æ
Section 8,
page 55).
V
Turn off the main gas supply cock and secure to pre-
vent it being inadvertently turned on again.
V
Allow boiler to cool.
V
Remove the trap from condensate pan drain outlet.
V
Place a bucket under the condensate pan outlet.
Fig. 56 Removing the trap
1
Trap
2
Condensate pan
Boiler
rating
Differential pressure in inches W.C. (Pa)
90-4
1.45 (360)
120-4
1.85 (460)
160-5
2.21 (550)
200-6
2.13 (530)
240-7
2.17 (540)
280-8
2.25 (560)
Tab. 15 Cleaning threshold – differential pressure
7 747 010 720-69.2RS
1
2
Содержание Logano plus GB312
Страница 121: ...Logano plus GB312 Technical specifications are subject to change without prior notice 121 Notes ...
Страница 122: ...Logano plus GB312 Technical specifications are subject to change without prior notice 122 Notes ...
Страница 123: ...Logano plus GB312 Technical specifications are subject to change without prior notice 123 Notes ...