Hot Melt Unit with Universal Control
1.
Turn off power to unit and open lid to electronics cabinet.
2.
Locate Control Board (151xx650) on the back of the Keypad. See figure below.
3.
Run flying lead end of the included Handgun Switch Cable Assembly up to the Control Board. If
your Handgun Switch Cable Assembly has a flange mounted connector, install it in place of the
knockouts provided in the back panel of the unit. Use hardware provided with kit.
4. If the cable assembly has a flange-mounted connector, route the cable assembly along the inside of
the unit, as shown.
Input 1
Input 2
Input 3
Input 4
Pin 2 (I1): Orange
Pin 5 (I2): Orange
Pin 8 (I3): Orange
Pin 11 (I4): Orange
Pin 3 (GND): Yellow
Pin 6 (GND): Yellow
Pin 9 (GND): Yellow
Pin 12 (GND): Yellow
Cable Connections
5.
Choose which of the four inputs that you want to connect to. Then connect the Yellow and Orange
wires from the Cable Assembly to the programmable inputs connector J23 on the Control Board as
follows.
If you use two Handguns and want both to activate an input, install the yellow and orange wires from each
cable in parallel.
If you want to use one Handgun Switch for two different functions (ie Pump On/Off and Auto Setback), then
connect to one of the inputs as shown in step 4; then run a jumper wire from where the Orange wire is landed
to the other input you want to use (I1-Pin 2, I2-Pin 5, I3-Pin 8, or I4-Pin 11).
6.
Discard the jumper wires included with the kit..
Summary of Contents for D4
Page 1: ...D4 Hot Melt Unit Manual Number MM147 Revision Date 6 2018 ...
Page 4: ......
Page 10: ...Table of Contents MM147 D4 Hot Melt Unit 10 Module Status LED 170 Link Activity LED 170 ...
Page 20: ...Section 2 Safety and Use MM147 D4 Hot Melt Unit 20 ...
Page 22: ...Section 3 Basic Features MM147 D4 Hot Melt Unit 22 ...
Page 35: ...MM147 D4 Hot Melt Unit Section 5 Setup 35 Section 5 Setup Control Panel ...
Page 42: ...Section 5 Setup MM147 D4 Hot Melt Unit 42 Set Language Continued Next Page ...
Page 43: ...MM147 D4 Hot Melt Unit Section 5 Setup 43 Set Language Continued ...
Page 44: ...Section 5 Setup MM147 D4 Hot Melt Unit 44 Set Temperature Units ...
Page 47: ...MM147 D4 Hot Melt Unit Section 5 Setup 47 Hose Valve Temperature Continued ...
Page 54: ...Section 5 Setup MM147 D4 Hot Melt Unit 54 Beacon Alarm Setup Continued ...
Page 55: ...MM147 D4 Hot Melt Unit Section 5 Setup 55 Beacon 2 ...
Page 70: ...Section 5 Setup MM147 D4 Hot Melt Unit 70 Sequential Start Valve ...
Page 100: ...Section 6 Operation MM147 D4 Hot Melt Unit 100 ...
Page 106: ...Section 7 Maintenance MM147 D4 Hot Melt Unit 106 ...
Page 110: ...Section 9 Specifications MM147 D4 Hot Melt Unit 110 Dimensions ...
Page 112: ...Section 10 Part Number List MM147 D4 Hot Melt Unit 112 D4 Unit ...
Page 113: ...MM147 D4 Hot Melt Unit Section 10 Part Number List 113 D4 Unit Continued ...
Page 120: ...Section 10 Part Number List MM147 D4 Hot Melt Unit 120 D4 Base Unit 776xx392 ...
Page 142: ...Section 11 Warranty MM147 D4 Hot Melt Unit 142 ...
Page 144: ...Section 12 Service MM147 D4 Hot Melt Unit 144 ...
Page 146: ...Appendix A Password Levels MM147 D4 Hot Melt Unit 146 Setting Level 0 as Default Continued ...
Page 148: ...Appendix B Power Requirements MM147 D4 Hot Melt Unit 148 ...
Page 150: ...Appendix C Instruction Sheets for Option Kits MM147 D4 Hot Melt Unit 150 ...
Page 208: ...5 Valco Melton IS0343 Anybus Installation Installation Continued ...
Page 245: ...Appendix E Communication Protocols Modus MM147 D4 Hot Melt Unit 162 ...