Page 63 of 101 pages
Preliminary Inspection
Caution!
Only qualified personnel or authorized electrician are permitted to perform
this inspection.
After installation and prior to putting the machine into operation, the following
preparing and checkout procedure is to be fulfilled.
♦
Check that the water inlets and the drain outlets are correctly connected
to the utilities and the manual taps on the external lines and on the
autoclave piping are open.
♦
Check that the manual bypass screws (on the base of the pilot solenoid
valves) are set in neutral position, i.e. the slit on the head of the screw is
set in horizontal position.
♦
Search for leaks and fix piping joints if necessary.
♦
Check Grounding!! (see par
. 10.2).
♦
Check insulation!!(see par
10.2
).
♦
Check at the electrical network switchboard, if the circuit of the autoclave
is switched on and fuses or circuit breakers are not interrupted, if the
correct voltages are present in the autoclave-generator control box,
according to the specifications.
♦
Check if circuit breakers in the control box are switched on.
If the results of the above checkouts are positive, the autoclave is ready for
operation.