Chapter 2 Pre-installation considerations
28
BAS-APG001-EN
Table 5. Sample automatic smoke control matrix (dedicated)
Table 6. Sample automatic smoke control matrix (nondedicated)
Equipment
First smoke zone in alarm
Zone 1
Zone 2
Zone 3
Zone 4
Main sup fan
On
On
On
On
Main R/E fan
On
On
On
On
Stair press fan
On
On
On
On
1st flr sup dmpr
Close
Open
Close
Close
1st flr ret dmpr
Open
Close
Close
Close
2nd flr sup dmpr
Open
Close
Open
Close
2nd flr ret dmpr
Close
Open
Close
Close
3rd flr sup dmpr
Close
Open
Close
Open
3rd flr ret dmpr
Close
Close
Open
Close
4th flr sup dmpr
Close
Close
Open
Close
4th flr ret dmpr
Close
Close
Close
Open
Smoke zone 1
Alarm
Adjacent
Unaffected
Unaffected
Smoke zone 2
Adjacent
Alarm
Adjacent
Unaffected
Smoke zone 3
Unaffected
Adjacent
Alarm
Adjacent
Smoke zone 4
Unaffected
Unaffected
Adjacent
Alarm
Equipment
First smoke zone in alarm
Zone 1
Zone 2
Zone 3
Zone 4
Main sup fan
On
On
On
On
Main R/E fan
On
On
On
On
Stair press fan
On
On
On
On
1st flr sup dmpr
Open
Open
Open
Open
1st flr ret dmpr
Open
Open
Open
Open
2nd flr sup dmpr
Open
Open
Open
Open
2nd flr ret dmpr
Open
Open
Open
Open
3rd flr sup dmpr
Open
Open
Open
Open
3rd flr ret dmpr
Open
Open
Open
Open
4th flr sup dmpr
Open
Open
Open
Open
4th flr ret dmpr
Open
Open
Open
Open
Smoke zone 1
Alarm
Adjacent
Open
Open
Smoke zone 2
Adjacent
Alarm
Adjacent
Open
Smoke zone 3
Open
Adjacent
Alarm
Adjacent
Smoke zone 4
Open
Open
Adjacent
Alarm
Summary of Contents for Engineered Smoke Control System
Page 1: ...BAS APG001 EN Applications Guide Engineered Smoke Control System for TRACER SUMMIT ...
Page 2: ......
Page 6: ......
Page 12: ...Contents vi BAS APG001 EN ...
Page 30: ...Chapter 1 Smoke control overview 18 BAS APG001 EN ...
Page 48: ...Chapter 3 Installation diagrams 36 BAS APG001 EN Figure 14 Tracer MP581 to FSCS wiring ...
Page 50: ...Chapter 3 Installation diagrams 38 BAS APG001 EN Figure 15 Tracer MP581 to FACP wiring ...
Page 57: ...Wiring high voltage ac power BAS APG001 EN 45 Figure 19 AC wiring ...
Page 59: ...EMI RFI considerations BAS APG001 EN 47 Figure 20 Checking the earth ground ...
Page 75: ...EMI RFI considerations BAS APG001 EN 63 Figure 31 Checking the earth ground ...
Page 96: ...Chapter 5 Installing the Tracer MP581 programmable controller 84 BAS APG001 EN ...
Page 110: ...Chapter 6 Installing the EX2 expansion module 98 BAS APG001 EN ...
Page 123: ...End process verification BAS APG001 EN 111 Figure 61 ast actuator fail checkb 3 13 06 ...
Page 132: ...Chapter 7 Programming 120 BAS APG001 EN ...
Page 151: ...Understanding bindings BAS APG001 EN 139 Figure 79 Mixed subnet node and group bindings ...
Page 152: ...Chapter 8 Network variable bindings 140 BAS APG001 EN ...
Page 154: ...Appendix A References 142 BAS APG001 EN ...
Page 155: ......