Chapter 5 Installing the Tracer MP581 programmable controller
74
BAS-APG001-EN
Wiring LonTalk to the Tracer MP581
IMPORTANT
When installing the Tracer MP581 controller in areas of high electro-
magnetic interference (EMI) and radio frequency interference (RFI), fol-
low the additional installation instructions in “EMI/RFI considerations”
on page 62.
To wire the LonTalk link:
1.
At the first Tracer MP581 on the link, complete the following steps:
•
Connect the white wire to the first (or third) LonTalk screw termi-
nal as shown in Figure 37.
•
Connect the black wire to the second (or fourth) LonTalk screw
terminal.
•
If this is the first LonTalk controller on the daisy chain, place a
105
Ω
termination resistor across the LonTalk screw terminals.
Figure 37. Wiring the first device to the LonTalk connection on the
termination board
2.
At the next Tracer MP581 (or other LonTalk controller) on the link:
•
Connect the white wires to the first and third LonTalk screw ter-
minals (as shown in Figure 38 on page 75).
•
Connect the black wires to the second and fourth LonTalk screw
terminals.
Note:
Although LonTalk links are not polarity sensitive, we recom-
mend that you keep polarity consistent throughout the site.
Note:
Place a 105
Ω
termination
resistor at the first and last LonTalk
device on the daisy chain. Termination
resistors require insulation, such as
heat shrink tubing, to avoid accidental
shorts to other conductors.
Summary of Contents for Engineered Smoke Control System
Page 1: ...BAS APG001 EN Applications Guide Engineered Smoke Control System for TRACER SUMMIT ...
Page 2: ......
Page 6: ......
Page 12: ...Contents vi BAS APG001 EN ...
Page 30: ...Chapter 1 Smoke control overview 18 BAS APG001 EN ...
Page 48: ...Chapter 3 Installation diagrams 36 BAS APG001 EN Figure 14 Tracer MP581 to FSCS wiring ...
Page 50: ...Chapter 3 Installation diagrams 38 BAS APG001 EN Figure 15 Tracer MP581 to FACP wiring ...
Page 57: ...Wiring high voltage ac power BAS APG001 EN 45 Figure 19 AC wiring ...
Page 59: ...EMI RFI considerations BAS APG001 EN 47 Figure 20 Checking the earth ground ...
Page 75: ...EMI RFI considerations BAS APG001 EN 63 Figure 31 Checking the earth ground ...
Page 96: ...Chapter 5 Installing the Tracer MP581 programmable controller 84 BAS APG001 EN ...
Page 110: ...Chapter 6 Installing the EX2 expansion module 98 BAS APG001 EN ...
Page 123: ...End process verification BAS APG001 EN 111 Figure 61 ast actuator fail checkb 3 13 06 ...
Page 132: ...Chapter 7 Programming 120 BAS APG001 EN ...
Page 151: ...Understanding bindings BAS APG001 EN 139 Figure 79 Mixed subnet node and group bindings ...
Page 152: ...Chapter 8 Network variable bindings 140 BAS APG001 EN ...
Page 154: ...Appendix A References 142 BAS APG001 EN ...
Page 155: ......