Chapter 5 Installing the Tracer MP581 programmable controller
76
BAS-APG001-EN
Installing the circuit board
The main circuit board is not installed in the Tracer MP581 enclosure
when it ships. You can store the circuit board in the office while the enclo-
sure is mounted and wired. After wiring has been completed, connect the
circuit board to the termination board.
To install the circuit board:
1.
Open the enclosure door.
2.
Verify that the 24 Vac power cable is not connected to the termination
board (see Figure 41 on page 78).
3.
Hold the top plastic frame, which holds the circuit board, at a 90°
angle to the bottom frame as shown in Figure 39.
Figure 39. Connecting the cables
4.
Connect the 60-pin cable to the 60-pin slot, then connect the 20-pin
cable to the 20-pin slot.
The connectors fit only one way. If you have difficulty connecting
them, make sure that the plastic grooves line up with the slots.
Summary of Contents for Engineered Smoke Control System
Page 1: ...BAS APG001 EN Applications Guide Engineered Smoke Control System for TRACER SUMMIT ...
Page 2: ......
Page 6: ......
Page 12: ...Contents vi BAS APG001 EN ...
Page 30: ...Chapter 1 Smoke control overview 18 BAS APG001 EN ...
Page 48: ...Chapter 3 Installation diagrams 36 BAS APG001 EN Figure 14 Tracer MP581 to FSCS wiring ...
Page 50: ...Chapter 3 Installation diagrams 38 BAS APG001 EN Figure 15 Tracer MP581 to FACP wiring ...
Page 57: ...Wiring high voltage ac power BAS APG001 EN 45 Figure 19 AC wiring ...
Page 59: ...EMI RFI considerations BAS APG001 EN 47 Figure 20 Checking the earth ground ...
Page 75: ...EMI RFI considerations BAS APG001 EN 63 Figure 31 Checking the earth ground ...
Page 96: ...Chapter 5 Installing the Tracer MP581 programmable controller 84 BAS APG001 EN ...
Page 110: ...Chapter 6 Installing the EX2 expansion module 98 BAS APG001 EN ...
Page 123: ...End process verification BAS APG001 EN 111 Figure 61 ast actuator fail checkb 3 13 06 ...
Page 132: ...Chapter 7 Programming 120 BAS APG001 EN ...
Page 151: ...Understanding bindings BAS APG001 EN 139 Figure 79 Mixed subnet node and group bindings ...
Page 152: ...Chapter 8 Network variable bindings 140 BAS APG001 EN ...
Page 154: ...Appendix A References 142 BAS APG001 EN ...
Page 155: ......