BAS-APG001-EN
31
Chapter 3
Installation diagrams
Smoke control system overview
An engineered smoke control system can be added on to a Tracer
Summit
™
building automation system. The system layout, wiring
requirements, and capacities for smoke control applications differ from
Tracer Summit systems that do not employ smoke control.
A smoke control installation includes a Trane building control unit
(BCU), the Tracer MP581 programmable controller, and wiring. These
devices should be wired on the smoke control communication link.
Devices that are a part of the Tracer Summit system, but are not used by
the smoke control system, must be on a separate communication link.
IMPORTANT
For dedicated smoke control system, only Tracer MP581s used for
smoke control are allowed on the LonTalk communication link. Tracer
MP581s and other LonTalk UCMs not involved in smoke control
must
be connected to other BCUs. A nondedicated smoke control system can
have other LonTalk devices connected to the communication link.
Installation diagrams consist of system riser and system termination
diagrams. These diagrams provide requirements and restrictions to the
installer.
Summary of Contents for Engineered Smoke Control System
Page 1: ...BAS APG001 EN Applications Guide Engineered Smoke Control System for TRACER SUMMIT ...
Page 2: ......
Page 6: ......
Page 12: ...Contents vi BAS APG001 EN ...
Page 30: ...Chapter 1 Smoke control overview 18 BAS APG001 EN ...
Page 48: ...Chapter 3 Installation diagrams 36 BAS APG001 EN Figure 14 Tracer MP581 to FSCS wiring ...
Page 50: ...Chapter 3 Installation diagrams 38 BAS APG001 EN Figure 15 Tracer MP581 to FACP wiring ...
Page 57: ...Wiring high voltage ac power BAS APG001 EN 45 Figure 19 AC wiring ...
Page 59: ...EMI RFI considerations BAS APG001 EN 47 Figure 20 Checking the earth ground ...
Page 75: ...EMI RFI considerations BAS APG001 EN 63 Figure 31 Checking the earth ground ...
Page 96: ...Chapter 5 Installing the Tracer MP581 programmable controller 84 BAS APG001 EN ...
Page 110: ...Chapter 6 Installing the EX2 expansion module 98 BAS APG001 EN ...
Page 123: ...End process verification BAS APG001 EN 111 Figure 61 ast actuator fail checkb 3 13 06 ...
Page 132: ...Chapter 7 Programming 120 BAS APG001 EN ...
Page 151: ...Understanding bindings BAS APG001 EN 139 Figure 79 Mixed subnet node and group bindings ...
Page 152: ...Chapter 8 Network variable bindings 140 BAS APG001 EN ...
Page 154: ...Appendix A References 142 BAS APG001 EN ...
Page 155: ......