Wiring inputs and outputs
BAS-APG001-EN
67
Wiring universal inputs
The Tracer MP581 controller has 12 universal inputs. Use the Rover ser-
vice tool to configure inputs for analog or binary operation.
The common terminals on the Tracer MP581 termination board are con-
nected to the metal enclosure by means of a ground screw. Shield wires
should be connected to a common terminal. Table 17 shows the load the
Tracer MP581 places on sensors.
Wiring binary inputs
Use binary inputs to monitor statuses, such as fan on/off and alarm
resets.
To wire a binary input:
1.
Connect the common wire to a common terminal as shown in
Figure 34.
Note that, because the common terminals are in parallel, you can
wire the common wire to any available common terminal.
2.
Connect the shield wire to a common terminal at the termination
board and tape it back at the input device.
3.
Connect the signal wire to an available input terminal (IN1–IN12).
4.
Use the Rover service tool to configure the input for binary operation.
Figure 34. Wiring a binary input
Table 17. Load placed on sensors
Input type
Load on sensor
Vdc (linear)
21 k
Ω
mA (linear)
221
Ω
< 1000 ft
(300 m)
Binary switch
Signal
Common
Shield
Tape back shield
NOTE: To reduce the potential for transients, locate input
devices in the same room with the Tracer MP581.
Summary of Contents for Engineered Smoke Control System
Page 1: ...BAS APG001 EN Applications Guide Engineered Smoke Control System for TRACER SUMMIT ...
Page 2: ......
Page 6: ......
Page 12: ...Contents vi BAS APG001 EN ...
Page 30: ...Chapter 1 Smoke control overview 18 BAS APG001 EN ...
Page 48: ...Chapter 3 Installation diagrams 36 BAS APG001 EN Figure 14 Tracer MP581 to FSCS wiring ...
Page 50: ...Chapter 3 Installation diagrams 38 BAS APG001 EN Figure 15 Tracer MP581 to FACP wiring ...
Page 57: ...Wiring high voltage ac power BAS APG001 EN 45 Figure 19 AC wiring ...
Page 59: ...EMI RFI considerations BAS APG001 EN 47 Figure 20 Checking the earth ground ...
Page 75: ...EMI RFI considerations BAS APG001 EN 63 Figure 31 Checking the earth ground ...
Page 96: ...Chapter 5 Installing the Tracer MP581 programmable controller 84 BAS APG001 EN ...
Page 110: ...Chapter 6 Installing the EX2 expansion module 98 BAS APG001 EN ...
Page 123: ...End process verification BAS APG001 EN 111 Figure 61 ast actuator fail checkb 3 13 06 ...
Page 132: ...Chapter 7 Programming 120 BAS APG001 EN ...
Page 151: ...Understanding bindings BAS APG001 EN 139 Figure 79 Mixed subnet node and group bindings ...
Page 152: ...Chapter 8 Network variable bindings 140 BAS APG001 EN ...
Page 154: ...Appendix A References 142 BAS APG001 EN ...
Page 155: ......