TELELIFT 3713 SX
REPAIR PROCEDURES
7
Document 57.4402.9200 - 1
st
Edition 10/2006
INDEX
7.1
TIME SCHEDULE
Job
Operators
Expected
needed
time (h)
change the ignition key
1
1,00
change the speed switch
1
0,30
change the lights and horn switch
1
0,30
change the overload warning system display
1
0,15
re-calibrate the 3B6 system
1
1,00
change the load cell
1
2,00
change the overload warning system display and calibrate
1
1,00
change the joystick levers
1
0,30
change the deadman button
1
0,30
change the joystick movement switch pushbutton
1
0,30
change the brake pump
1
1,00
change the low boom sensor
1
0,30
change the boom lifting cylinder
2
2,15 each
change the boom lifting cylinder kit
(complete overhaul)
1
1,30
change the block valve of the boom lifting cylinder
1
0,30
change the cylinder inside the boom
2
2,50 each
change the extension cylinder kit inside the boom
1
1,30
change the block valve of the extension cylinder
inside the boom
1
0,30
change the extension cylinder on the boom
2
1,00 each
change the extension cylinder kit on the boom
1
1,30
change the valve of the extension cylinder on the boom
1
0,30
change the re-sequencing valve of the
extension cylinder inside the boom
1
2,30
change the re-sequencing valve of the
extension cylinder on the boom
1
2,30
change the fork pitching cylinder
1
1,30
change the fork pitching cylinder kit
1
1,30
change the valve of the fork pitching cylinder
1
0,30
change the attachment locking cylinder
1
1,00
change the attachment locking cylinder kit
1
1,30
change the block valve of the attachment locking cylinder
1
0,30
change the outrigger up/down mov. cylinder
1
1,30
change the outrigger up/down mov. cylinder kit
1
1,30
change the valve of the outrigger up/down mov. cylinder
1
0,30