Parameterization
9.3 Parameters
3KC ATC6300 transfer control device
136
Manual, 03/2018, L1V30535632002A-01
9.3.9
P09 - Automatic test
P09 –
Automatic
test
Designation on ATC
display
Description
Unit
Default Range
P09.01
Auto test enable
Enabling the automatic test
– Enables the execution of the periodic test.
This parameter can be modified directly from
the front operator panel, without invoking the
setup procedure. Its current status is displayed
on the corresponding display page, see chapter
Automatic test (Page 51).
OFF
OFF / ON
P09.02
Auto test period
Interval between performing the TESTS
– Interval between two periodic tests. If the test
is not enabled on the day it becomes due, the
period is extended to the next enabled day.
7
1gg-60gg
P09.03
Auto Test Monday
TEST execution on Monday
- Enables the performance of the automatic test
on the individual days of the week.
OFF means that the test is not performed on
that day of the week.
ON
OFF / ON
P09.04
Auto Test Tuesday TEST execution on Tuesday
- see Parameter 09.03
ON
OFF / ON
P09.05
Auto Test Wednes-
day
TEST execution on Wednesday
- see Parameter 09.03
ON
OFF / ON
P09.06
Auto Test Thursday TEST execution on Thursday
- see Parameter 09.03
ON
OFF / ON
P09.07
Auto Test Friday
TEST execution on Friday
- see Parameter 09.03
ON
OFF / ON
P09.08
Auto Test Saturday TEST execution on Saturday
- see Parameter 09.03
ON
OFF / ON
P09.09
Auto Test Sunday
TEST execution on Sunday
- see Parameter 09.03
ON
OFF / ON
P09.10
Auto test hour
Hour of TEST start
- Specifies the hours and the minutes for the
start of the periodic test.
h
12
00-23
P09.11
Auto test minute
Minutes of TEST start
- see Parameter 09.11
min
00
00-59