Commissioning
5.5 Commissioning using the BOP
Control Units CU240S
58
Operating Instructions, 07/2008 - FW 3.2, A5E00766042B AD
5.5.2
Overview Commissioning with the BOP
Commissioning overview
A differentiation is made between the following scenarios when commissioning the inverter
via BOP:
Single commissioning
● Basic commissioning
– Quick commissioning
– Calculating the motor data,
- automatically via Motor data identification
- or manually via P0340
– Speed control optimization
● Commissioning the application
● Commissioning the fail-safe functions (only in fail-safe applications)
Series commissioning
● Uploading the parameter set
● Downloading the parameter set
Reset parameters to factory settings
● Sets the parameter settings of the inverter settings back to the delivery state.
When commissioning, initially, a commissioning should be performed.
If there is no appropriate parameter set available for series commissioning, a single
commissioning must be carried-out.
With the function "quick commissioning", the inverter is adapted to the motor and important
technological parameters are set.
The step "commissioning the application" should only be performed, if the inverter–motor
combination provides a satisfactory result.